Visitable Housing
Cost Estimate summary
June 2007
This report
summarizes our findings related to the cost and market implications of
incorporating basic visitable features
into two single family detached houses in Manitoba. It was prepared at the
request of Manitoba Housing and Renewal Corporation (MHRC). Refer to Appendix 1
for the mandatory requirements for basic visitability.
Because this
cost analysis is a case study, based on two specific model homes and sites,
caution should be exercised in generalizing the results. For example, the laned
lot solution involved adding a side door, which would not be required in all or
even the majority of cases of visitable construction.
For this
analysis we used Waverley West sites and typical housing units designed for
this development as models. Two test sites were selected: one with a back lane
and one without, to observe the effect of different grading patterns on costs.
Both are gently sloping (approx. 2% grade) midblock sites, avoiding the
non-typical conditions of corner lots. The laned lot has split drainage, with
the high point in the front yard. The non-laned lot provides standard front to
back drainage.

Lot
without Backlane
Lot with Backlane
Figure
1. Waverley West lots used for the cost analysis
House plans
were provided by Qualico Homes, and selected to represent typical features,
widths, door types, and finish floor grades within the current market. We
rejected units that had too many visitable features incorporated this could
skew the results and make this analysis less useful.


Figure
2a: Qualico plans selected for the cost analysis. The Broadview DG-11 model
currently in development was used for the non-laned lot


Figure
2b: Qualico plans selected for the cost analysis. The Broadview RG-70 model
currently in development was used for the laned lot.
Interior
revisions were designed and costed by Lanny Silver, architect, in consultation
with Edgar Rosales of Qualico Homes. Hilderman Thomas Frank Cram developed
designs for the external visitable features, based on original design drawings
prepared by Stantec Consulting. The designs and preliminary costs were reviewed
by Qualico, and Dave Rapson reviewed the work for compliance with mandatory
requirements as identified in our policy document (April, 2006).
Determining
the best accessible path of travel to the door took some effort. On each site,
we looked for opportunities to create an accessible path that added amenities
such as planting areas and seating spaces, while maintaining continuity with
adjacent properties. Because ramps were not used, some lowering of the finish
floor grades - between 3.5 (83mm) and 6 (150mm) - was required to keep the
walkway grades at 5% or less. Earthwork berm grades are 20% or shallower: well
within mowable limits. Landings were priced as cast-in-place concrete, unless
they were extensions to decks or porches, in which case they will be
constructed of matching
materials.
Walkways were also priced as cast-in-place concrete.
Front door
access is only possible on the laned lot. In all cases, the side yard requires
either a retaining wall or mirrored treatment on the house next door to
accommodate the grade changes. This suggests that there will be economic
benefit in designing and building visitable sites in pairs.
Figure 3
shows a curving 5% walkway leading to the side door. This scheme provides a
formal front planting space and good access to the front door (reducing the
number of stairs). Subdrainage will also be required at the side entrance, or a
trough on the property line to move water past or under the raised grade. Note
that this option requires relocating the garage and therefore would require
some engineering fees, as indicated on the spreadsheet (Tables 1a-c).

Figure
3: Visitable design concept for Non-Laned Lot.
Notes:
elevations
are in metres
elevation
99.92 finished floor grade is 83mm (3 1/4) below grade indicated on Qualico
plan.
Two options
were priced for this lot. Option A (Figure 4a) gives access to the front door
from the back lane. It is a straight run, and would require construction of an
extension on the front porch for the most elegant connection. No amenity space
is created by this option. Subdrainage is not
required, as
this lot has split drainage.
Option B
(Figure 4b) takes advantage of the large sideyard to provide a shallow (4.2%)
accessible route from the front yard to the back deck. This option is costly
because it requires a large extension to the deck, and probably would require a
variance, but it also creates the most marketable amenity in the double-sized
deck.

Figure
4a: Visitable design concept for Laned Lot - Option A.
Notes:
elevations
are in metres
elevation
99.85 finished floor grade is 150mm (6) below grade indicated on Qualico plan.

Figure
4b: Visitable design concept for Laned Lot - Option B.
Notes:
elevations
are in metres
elevation
100.00 finished floor grade is as indicated on the Qualico plan
Modifying
the interiors was to follow the minimum requirement of allowing access and
visit capability. The interior modifications to most of the homes in this
development will be minimal as the homes have very generous room sizes and
circulation space. Most of the interior cost resulted from modifying existing
drawings to fit the site and raising the grade at the perimeter. As an example,
the Option #1 floor plan resulted from flipping the two car garage from the
right side of the original plan to the left side and tucking it into the
existing jog. The solution resulted in having to add another door and landing
for the new side entrance. A concrete foundation upstand was required at this
location.
No Step Entrance: Required
additional exterior door 2-8x 6-8 with low profile threshold and lever
lockset. When grade is brought up to the Main floor a concrete upstand would be
required to maintain an 8 separation from finished grade and any wood or
products affected by water (such as floor joists, siding, sheathing and wood
framing etc)
Washroom: The washroom met visitable requirements
but the pocket door was changed to a swing door with lever lockset , an
enhanced feature that we felt would not cost more than the pocket door.
Circulation: The designs used, in some cases, seemed to
indicate a dropped foyer. This would not be suitable for Visitable design and
was deleted. This change should not result in extra cost.
No Step Entrance: The existing design only required a low
threshold door.
Washroom: The washroom in this unit required a
modification to the design. The washer/dryer had to be relocated or the kitchen
had to be reduced. We opted for relocating the washer/dryer.
Circulation: Within the unit, this was ample and no
changes were required.
This design
would require zoning approval for the wider than normal side yard. If this plan
were used the interior consideratiions would not change.
The costs
provided in this report are in addition to normal requirements, such as
driveway and sidewalk.
Table
1a: Costing - visitable design
concept
for Non-Laned Lot.
|
|
Item |
Size |
Extra Cost - Materials |
Extra Cost - Labour |
Unit Price |
Mark-up Overhead 25% |
Cost Estimate Total |
|
House |
Additional exterior door Framing |
|
$50.00 |
$50.00 |
- |
$25.00 |
$125 |
|
Door c/w access threshold + added weather-stripping |
2'10" x 6'8" |
$500.00 |
$100.00 |
- |
$150.00 |
$750.00 |
|
|
Washroom door c/w lever lockset |
2'8" x 6'8" |
$150.00 |
$100.00 |
- |
$60.00 |
$310.00 |
|
|
Modified floor joist detail (pocket in foundation wall) required
where finish grade is raised against foundation |
15 linear ft. by 10" height |
$150.00 |
$150.00 |
- |
$75.00 |
$375.00 |
|
|
Size |
Site Cast-in-place concrete walkway max. 5% grade, 4'8" wide |
145 sq. ft. |
- |
- |
$6.80 |
$245.00 |
$1,230.00 |
|
Reinforced concrete entry landing. Provision to ensure platform
does not settle or heave. |
12 cu. ft. |
- |
- |
$33.50 |
$100.00 |
$500.00 |
|
|
Drainage pipe |
18 linear ft. |
- |
- |
$45.50 |
$205.00 |
$1,025.00 |
|
|
Earthwork - assume site material |
185 cu. ft. |
- |
- |
$1.00 |
$45.00 |
$230.00 |
|
|
Concrete porch stairs |
7.5 cu. ft |
- |
- |
$33.50 |
$65.00 |
$315.00 |
|
|
Credits |
Credits Cast-in-place concrete walkway to front door |
55 sq. ft. |
- |
- |
$6.80 |
$95.00 |
$470.00 |
|
Reinforced concrete entry Landing |
4.5 cu ft. |
- |
- |
$33.50 |
$40.00 |
$190.00 |
|
|
Concrete porch stairs |
25 cu. ft. |
- |
- |
$33.50 |
$210.00 |
$1,050.00 |
|
|
Earthwork - 25% of grading attributed to standard site grading |
46 cu. ft. |
- |
- |
$1.00 |
$10.00 |
$55.00 |
|
|
TOTAL $3,095.00 |
|||||||
|
Optional |
Engineering services garage flipped |
- |
- |
- |
- |
- |
$500.00 |
|
Precast concrete block retaining wall |
75 sq. ft. |
|
|
$31.50 |
$590.00 |
$2,950.00 |
|
Table
1b: Costing - visitable design concept for Laned Lot - Option A.
|
|
Description |
Size |
Extra Costs- Materials |
Extra Costs- Labour |
Unit Price |
Mark-up Overhead |
Cost Estimate Total |
|
|
House |
Door c/w access threshold + added weather-stripping |
2'10"
x 6'8" |
$50.00 |
- |
- |
$13.00 |
$63.00 |
|
|
Design change washroom walls and plumbing |
- |
$200.00 |
$200.00 |
- |
$100.00 |
$500.00 |
||
|
30" Biofold doors where required by design |
30"
wide |
$150.00 |
$150.00 |
- |
$75.00 |
$375.00 |
||
|
Modified floor joist detail (pocket in foundation wall) required
where finish grade is raised against foundation |
50 linear ft. by 10" height |
$250.00 |
$500.00 |
- |
$185.00 |
$935.00 |
||
|
Site |
Cast-in-place concrete alkway max. 5% grade, 2'10" wide |
190
sq. ft. |
- |
- |
$6.80 |
$325.00 |
$1,615.00 |
|
|
Deck - standard + extension |
180
sq. ft |
- |
- |
$30.00 |
$1,350.00 |
$6,750.00 |
||
|
Earthwork - assume site material |
620
cu. ft. |
- |
- |
$1.00 |
$155.00 |
$775.00 |
||
|
Credits |
Standard deck |
150
sq. ft |
- |
- |
$30.00 |
$1,125.00 |
$5,625.00 |
|
|
Earthwork - 25% of grading attributed to standard site grading |
155
cu. ft |
- |
- |
$1.00 |
$40.00 |
$195.00 |
||
|
TOTAL
$5,193.00 |
||||||||
|
Optional |
Precast concrete block retaining wall - - $31.50 $790.00
$3,940.00 |
100
sq. ft. |
- |
- |
$31.50 |
$790.00 |
$3,940.00 |
|
Table
1c: Costing - visitable design
concept
for Laned Lot - Option B.
|
|
Description |
Size |
Extra Cost - Materials |
Extra Costs - Labour |
Unit Price |
Mark-up Overhead |
Cost Estimate Total |
|
House |
Door c/w access threshold + added weather-stripping |
2'10" x 6'8" |
$50.00 |
- |
- |
$13.00 |
$63.00 |
|
Design change washroom walls and plumbing |
- |
$200.00 |
$200.00 |
- |
$100.00 |
$500.00 |
|
|
30" Biofold doors where required by design |
30" wide |
$150.00 |
$150.00 |
- |
$75.00 |
$375.00 |
|
|
Modified floor joist detail (pocket in foundation wall) required
where finish grade is raised against foundation. |
50 linear ft. by 10" height |
$250.00 |
$500.00 |
- |
$185.00 |
$935.00 |
|
|
Site |
Cast-in-place concrete walkway max. 5% grade, 3'2" wide |
190 sq. ft. |
- |
- |
$6.80 |
$325.00 |
$1,615.00 |
|
Deck - standard + extension |
210 sq. ft. |
- |
- |
$30.00 |
$1,575.00 |
$7,875.00 |
|
|
Earthwork - assume site material |
680 cu. ft. |
- |
- |
$1.00 |
$170.00 |
$850.00 |
|
|
Variance application |
- |
- |
- |
- |
- |
$1,200.00 |
|
|
Credits |
Standard deck |
120 sq. ft. |
- |
- |
$30.00 |
$900.00 |
$4,500.00 |
|
Earthwork - 25% of grading attributed to standard site grading |
170 cu. ft. |
- |
- |
$1.00 |
$40.00 |
$210.00 |
|
|
TOTAL: $8,703.00 |
|||||||
|
Optional |
Precast concrete block retaining wall |
140 sq. ft. |
- |
- |
$31.50 |
$1,100.00 |
$5,510.00 |
Interior
costs are negligible if planned at the outset. The houseplans provided by
Qualico were essentially visitable on the interior, so these feature should
present no negative market implications. Sales agents should capitalize on
this, treating the accessibility of the main floor living spaces as a selling
point.
Most of the
additional costs we identified relate to creating the accessible route to the
door and the no step entry. In all the design case studies, these modifications
add value through creating more amenity space and more interest in the
landscape. Many buyers will appreciate the convenience and value of having the
walkways built by the developer, whose forces are mobilized on site and should
be able to offer a volume discount.
The case
studies lower the finished floor elevation by a maximum of 6 (150 mm), so
standard basement windows can be installed without window wells. This maintains
the elevated appearance and livability of basement spaces that is prized in
todays market. If full-sized egress basement windows are desired to allow a
basement bedroom, shallow window wells may be required.
Visitable
homes built in isolation without any pre-planning are the most expensive
option. The strategy of pairing visitable homes to avoid retaining walls along
the side yards should be considered if visitable homes are to be incorporated
into a development.
1. An
Accessible Path of Travel
·
A path of travel with a gentle grade
(maximum 1:20 or 5%) from the street, sidewalk, back lane, or the dwelling
units parking space to an accessible entrance into the dwelling unit. This
dwelling units entrance may be located at the front, side, rear, or through
the garage of the home. In certain situations, in order to gain access into the
dwelling unit, a ramp may be required;
·
The path of travel shall be firm, stable,
and slip resistant;
·
The path of travel shall be a minimum of
36 (915mm) in width (preferred 48 (1220mm));
·
The cross slope of the path of travel to
be at a maximum of 1:50 or 2%;
·
No steps shall occur along this path of
travel; and
·
No drop off or slopes over 1:20 shall
occur along the edge of the path of travel.
2. A No-Step
Entrance Area
·
An exterior landing entrance area with a
minimum clear area of 5-0 x 5-0 (1525mm x 1525mm) (preferred 7-6 x 76
(2285 x 2285mm));
·
A landing area that is firm, stable, and
slip resistant;
·
A landing area that has a slope in any
direction of no more than 1:50 (2%);
·
One no-step entrance at the entrance door;
·
A minimum 36 (915mm) clear width of the
entrance door;
·
A no or low profile threshold at the door.
Raised thresholds of 1/4 (6mm) or less do not require any special
requirements. Thresholds over 6mm to a maximum of 1/2 (13mm) must be beveled
at a maximum slope of 1:2 (50%). Less steep is recommended. Thresholds over
1/2 must be ramped similar to those requirements of curb ramps as outlined in
the references below;
3. Passable
Interior Circulation on the Main Floor
·
Interior doorways minimum 32 (810mm)
(preferred 33 1/2 (850mm)) clear width;
·
Clear passage throughout with a minimum
36 (915mm) (preferred 48 (1220mm)) clear width to access all main floor activity
areas, including the washroom. Where a turn is required by a person using a
wheelchair to access various rooms on the main floor sitting, dining,
entertaining and the washroom, the clear width should be at least 53 (1350mm).
1A ramp may be used in existing situations where the elevation
of the floor above
grade
is too great to be accessed a gently sloped walkway alone.
4. Access to
a Main Floor Washroom
·
A main floor washroom that a person using
a mobility device, such as a wheelchair, can enter, close the door, and use the
facilities. This would require a 5-0 (1520mm) turning circle in front of the toilet
with the washroom door not crossing the turning circle while being closed or
opened;
·
Clear space under wall-hung fixtures can
be included in the 5-0 (1520mm) requirement.
· The washroom must have at a minimum one sink and one toilet.